Bridge File Construction | |||||
Construction Year | Bridge File # | Land Location | Watercourse | New Structure Recommendation | Status |
2021 | 70833 | SW 12-15-23-4 | Long Coulee Creek | Culvert Conversion | Completed Spring 2021 |
2021 | 80085 | SW 4-17-18-4 | BRID Irrigation Canal | Culvert Conversion | Fall 2021 Construction |
2022 | 80081 | SW 7-17-18-4 | BRID Irrigation Canal | Culvert Conversion | Spring 2021 Construction |
2022 | 72669 | SE 16-17-25-4 | Tributary to West Arrowwood Creek | Culvert Replacement | Planning |
2022 | 70038 | NW 7-16-24-4 | Tributary to Long Coulee Creek | Culvert Replacement | Planning |
2023 | 75027 | SW 30-15-24-4 | Tributary to Long Coulee Creek | Culvert Replacement | Planning |
2023 | 75293 | SE 29-15-25-4 | Tributary to Little Bow River | Culvert Replacement | Planning |
2024 | 80429 | SW 29-20-22-4 | Cattle Crossing | Culvert Replacement | Planning |